Which of the following additional rules apply if you are erecting an amateur station antenna structure at a site at or near a public use airport?
You may have to notify the Federal Aviation Administration and register it with the FCC as required by Part 17 of the FCC rules✓Bonne réponse
You may have to enter the height above ground in meters, and the latitude and longitude in degrees, minutes, and seconds on the FAA website
You must file an Environmental Impact Statement with the EPA before construction begins
You must obtain a construction permit from the airport zoning authority per Part 119 of the FAA regulations
Explication
An antenna structure located near or at a public use airport, like one more than 60.96 meters above ground, may require notice to the Federal Aviation Administration and registration with the Commission under Part 17. The amateur rules contain no EPA impact statement and no airport construction permit, and the data entry details on the FAA site are not the legal requirement.